Laying out the plates.
Gableworth Design-Build30 pages / Fictional brand / Demo site by Sumo Studios
Start
Behind the counter
Small print
Weather days so far: 4. Float left before keys move: 6 working days.
| Task | Weeks | Dates | Status |
|---|---|---|---|
| Sitework and clearing | 1 to 3 | 2 Mar 2026 to 16 Mar 2026 | Done |
| Footings and foundation | 3 to 11 | 16 Mar 2026 to 11 May 2026 | Done |
| Sill and first-floor deck | 12 to 14 | 18 May 2026 to 1 Jun 2026 | Done |
| Wall and roof framing | 15 to 31 | 8 Jun 2026 to 28 Sept 2026 | In progress |
| Roofing and dry-in | 30 to 35 | 21 Sept 2026 to 26 Oct 2026 | In progress |
| Windows and exterior doors | 33 to 36 | 12 Oct 2026 to 2 Nov 2026 | Upcoming |
| Rough plumbing, electrical, heating and cooling | 35 to 44 | 26 Oct 2026 to 28 Dec 2026 | Upcoming |
| Cedar shingle and trim | 37 to 48 | 9 Nov 2026 to 25 Jan 2027 | Upcoming |
| Insulation | 45 to 46 | 4 Jan 2027 to 11 Jan 2027 | Upcoming |
| Drywall and plaster | 47 to 52 | 18 Jan 2027 to 22 Feb 2027 | Upcoming |
| Millwork and stair | 52 to 60 | 22 Feb 2027 to 19 Apr 2027 | Upcoming |
| Tile and stone | 54 to 60 | 8 Mar 2027 to 19 Apr 2027 | Upcoming |
| Flooring | 59 to 63 | 12 Apr 2027 to 10 May 2027 | Upcoming |
| Paint and finishes | 62 to 66 | 3 May 2027 to 31 May 2027 | Upcoming |
| Punch list and clean | 67 to 69 | 7 Jun 2027 to 21 Jun 2027 | Upcoming |
| Foundation inspection | 10 | 4 May 2026 | Done |
| Framing inspection | 33 | 12 Oct 2026 | Upcoming |
| Dry-in | 35 | 26 Oct 2026 | Upcoming |
| Rough inspections | 44 | 28 Dec 2026 | Upcoming |
| Insulation inspection | 46 | 11 Jan 2027 | Upcoming |
| Substantial completion | 67 | 7 Jun 2027 | Upcoming |
| Keys | 69 | 21 Jun 2027 | Upcoming |