Week 31: the frame is up and the roof is closing in.
Thursday 1 October 2026

Roof framing closed out Wednesday. Both wings are sheathed and the underlayment has started on one roof; the other gets it Monday. Framing inspection is booked for Tuesday 13 October. Windows land the week of 26 October.
Message LuisFraming inspection, Tuesday 13 October · Dry-in, week 35
Pending, not included: CO-03 +$9,632.
Sample data · The contingency sits outside the contract.
Roof sheathing on both wings, and the underlayment started on one of them. Framing inspection booked for 13 October.
Wall sheathing on. Two of the crew on the ridge setting the last rafter pairs.
Second floor and roof framing. Rafters are 2x12 at 16 in.
Yes. I will bring a bucket so you can see the limestone wet and dry.
Luis · 30 SeptemberCO-03 is in the portal. Sign by the 9th and we frame it with the rest of the landing.