| No. | Milestone | Share | Base | Changes added | Total | Status |
|---|---|---|---|---|---|---|
| 1 | Deposit at contract | 10% | $296,200 | $0 | $296,200 | Paid 6 Feb 2026 |
| 2 | Foundation complete | 15% | $444,300 | $0 | $444,300 | Paid 15 May 2026 |
| 3 | Framing and roof dry-in | 20% | $592,400 | $6,800 | $599,200 | Next: at dry-in, about 26 October (week 35)Requested at dry-in, about 26 October. |
| 4 | Rough mechanicals inspected | 15% | $444,300 | $0 | $444,300 | Scheduled, week 44 |
| 5 | Insulation and drywall | 10% | $296,200 | $0 | $296,200 | Scheduled, week 52 |
| 6 | Finishes | 20% | $592,400 | $0 | $592,400 | Scheduled, week 66 |
| 7 | Substantial completion | 7% | $207,340 | $0 | $207,340 | Scheduled, week 67 |
| 8 | Final, after the punch list | 3% | $88,860 | $0 | $88,860 | Scheduled, within 30 days of keys |
| Current total | $2,968,800 | |||||
How draws work: each draw is requested when its milestone is inspected or photographed. Payment is due within 10 days by ACH from the account on file.
See the Draw 3 invoice emailDraws are paid by ACH from the account named in the contract. The portal never asks for bank or card numbers.