Laying out the plates.
Gableworth Design-Build30 pages / Fictional brand / Demo site by Sumo Studios
Start
Behind the counter
Small print
The engineer found a soft pocket of soil under the north-east corner. Footings there go 30 inches deeper, per the letter of 17 April.
3 working days. The superintendent carries the change into the job schedule.
Funded from the contingency, which sits outside the contract.
Signed by Rachel and James · 20 Apr 2026 · Countersigned by Tom Reidy.